Wednesday, January 28, 2026

Portfolio Project Schedule

 Since we’ve already started our portfolio projects, we made our schedule for the next upcoming weeks. Not only to keep ourselves on track but also have a checklist that we can follow weekly. It goes as follows:

Week One (1/16-1/23)

  • Initial research about genre
    • Science Fiction genre (how films in this genre are made, marketed, and distributed)
  • Brainstorming ideas for the project
  • Scheduling 

Week Two (1/26-2/1)

  • Write the script
  • Storyboard
  • Scope out locations
  • Schedule filming days

Week Three (2/2-2/8)

  • Finish the script
  • Filming

Week Four (2/9-2/15)

  • Filming for the film opening
  • Start editing at some capacity

Week Five (2/16-2/22)

  • Continue editing
  • Analyze first cut
  • Revise

Week Six (2/23-3/1)

  • Creative Critical Reflection
  • Work on Slideshow
    • Create script for voice over
    • Research things to discuss for the director's cut

Week Seven (3/2-3/8)

  • Creative Critical Reflection
    • Finish slideshow
    • Record voice over
    • Research the technologies integrated in the project

Week Eight (3/9-3/17)

  • Creative Critical Reflection
  • Our due date Friday before break

This is our schedule, hoping that there are no setbacks, but being realistic tells me otherwise. If there are any set backs I will make sure to update it on my blog as soon as possible. That’s all the updates for now. Bye!